Really appreciate the update.  Looks like steel columns are being delivered.  Which leads me to believe the footings/perimeter foundation is in place.

Edited by DeepGreen
Posted
48 minutes ago, DeepGreen said:

Really appreciate the update.  Looks like steel columns are being delivered.  Which leads me to believe the footings/perimeter foundation is in place.

Great eye! You are right. They are about 3 weeks behind because of rain! GMG 

Posted

It took what seemed like forever to finish my son’s high school IPF(75yd x 65yd playing surface and 52ft high) because the manufacturer wasn’t  able to keep up with demand, and kept delivering it in separate pieces.  It’s damn nice though and was worth the wait.

15822CF1-13B5-4425-9BA1-BF67E783C22C.png.3d01a913eff2088cecda23b5ac7b60b1.png

Has four Big Ass Fans.

8F755917-91C4-42E0-829F-28091F42CC19.png.8fc2f5d33edbb23d5be48a00e299439c.png

Has four 75 foot long batting cages suspended from the ceiling.

46ED445F-B4AC-47CD-8D4D-ABC4BD8A4891.png.5f1587cfb76a0afec835480bf20fe5ab.png

396BFEFA-AE0C-436D-B389-9F68CBBEB1D1.png.977b61e20ba5053decdeda5419771540.png

So as nice and as large as the Mean Green IPF is going to be I’ll be surprised if it’s completed by the end of August.

 

Rick

Posted
2 hours ago, trud1966 said:

well, that hardly looks indoors to me...I blame RV!

 

 

2 hours ago, trud1966 said:

well, that hardly looks indoors to me...I blame RV!

 

THANKS FOR PICTURES---KEEP THEM COMING

Posted
7 hours ago, FirefightnRick said:

It took what seemed like forever to finish my son’s high school IPF(75yd x 65yd playing surface and 52ft high) because the manufacturer wasn’t  able to keep up with demand, and kept delivering it in separate pieces.  It’s damn nice though and was worth the wait.

15822CF1-13B5-4425-9BA1-BF67E783C22C.png.3d01a913eff2088cecda23b5ac7b60b1.png

Has four Big Ass Fans.

8F755917-91C4-42E0-829F-28091F42CC19.png.8fc2f5d33edbb23d5be48a00e299439c.png

Has four 75 foot long batting cages suspended from the ceiling.

46ED445F-B4AC-47CD-8D4D-ABC4BD8A4891.png.5f1587cfb76a0afec835480bf20fe5ab.png

396BFEFA-AE0C-436D-B389-9F68CBBEB1D1.png.977b61e20ba5053decdeda5419771540.png

So as nice and as large as the Mean Green IPF is going to be I’ll be surprised if it’s completed by the end of August.

 

Rick

It probably won’t be ready for August, but it will be done by December when we need a warm place to practice for our College Footballs Playoff semifinal. 

  • Upvote 1
  • Skeptical Eagle 1
Posted
2 minutes ago, greenminer said:

Would have been cool if they set up a web cam.  I think they did this with Apogee construction, and were given the option to download a time lapse video.

Great idea... contact AD!

  • Upvote 1

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue. Please review our full Privacy Policy before using our site.